9/18/12

Trenches back filled!

GREEN STICKER from the City - we got clearance to back fill the trenches!

Framing Update

9/10/12

Plumbing & Water

Day 1 - 7 hours of trenching for water lines from the water well:
The turn to the corner of the garage:
Plumbing inside:
Day 2 - 4 hours trenching for the power line - separate trench needed for code:

9/4/12

Pastel Pasture

Framing in the Garage

Time for an update! Last weekend was Labor Day weekend and boy did we 'labor'. We finished the framing inside the building, next will be the water and electrical lines. Ones we had the City inspections we can then close all walls.
So here are some pictures:
Kitchen: Entrance door to the left, middle is entrance to restroom
Workshop: Double wide door
Another shot into the kitchen:
The travel trailer: